Case study, Ibeju-Lekki, Lagos

Ibeju coastal link road

11.6 kilometres of dual carriageway, side drains and four culverts, built through two rainy seasons.

11.6 kmlength
4culverts
₧7.4bncontract value
38,000 tasphalt laid

The brief

What the client needed

Handed over October 2024

A road across sand and swamp to open up new estates, with the rains due within weeks of the start. Communities along the route needed access every day of construction.

Our approach

How we built it

Drains first

Side drains and culverts were built ahead of the road, so the first rains drained instead of washing out fill.

Sand replacement

Over 2 kilometres of soft ground was dug out and replaced with compacted sand in tested layers.

Our own asphalt

A mobile asphalt plant on site cut haulage and let us pave in short dry windows.

Access every day

Temporary crossings and a community liaison officer kept every village connected.

Programme

Key dates

  1. Nov 2022Mobilisation and clearing
  2. Apr 2023Drains and culverts complete
  3. Dec 2023Earthworks complete
  4. Jul 2024Asphalt complete
  5. Oct 2024Handover

On site

Photographs

Tall buildings rising under a cloudy sky
An excavator digging soil
Two builders working together on site
They built the drains first and the road survived its first rainy season without a single washout.Example client, estate consortium
Who maintains the road?

We are under a three year maintenance contract with the estate consortium.

Did the project add street lights?

Yes, 290 solar street lights along both carriageways.