312 valves, one shutdown
Servicing every valve on a shallow-water platform during a 19-day shutdown, with the Onne workshop running day and night.
Shallow water, 2025
Platform shutdowns are expensive, so every hour counts. We surveyed every valve two months ahead and tagged each one with a QR code linked to its history, spares and procedure.
During the shutdown, valves that could be serviced in place were done by three offshore crews. The rest came to the Onne workshop by supply vessel, were stripped, lapped, rebuilt and pressure tested, and went back out within 48 hours.
The client received a digital record for every valve: photographs before and after, test charts and the technician’s name.
- Client
- An international operator
- Location
- Shallow water, off Bonny
- Scope
- Service 312 valves, replace 41
- Duration
- 19 days, on schedule
- Peak crew
- 58 people
- Safety
- Zero recordable injuries
Example project for this demo.
Every valve has a QR code now. Next shutdown starts with a scan, not a search.Summit project lead
E3Photographs
E4What we learned
- 01Plan around the window
The schedule was built backwards from the date access would close, not forwards from mobilisation.
- 02Move the camp with the work
Less travel means more working hours and fewer boat incidents.
- 03Inspect the same day
Same-day inspection means a repair is a short job, not a crisis.
E5Questions
Can we get the full lessons report?
Yes, with a request for quote, subject to the client’s agreement.
Who led the project?
A Summit project manager based in Port Harcourt, with a site lead on each front.
Next report
14 km of flowline in one dry season
Replacing a corroded flowline in mangrove swamp before the rains, with no lost-time injury and nine days in hand.
Tell us the scope.
An engineer replies within one working day with a draft scope, crew plan and price. Live jobs: call the operations room day and night.