Pipeline construction and integrity
From right-of-way clearing in the swamp to the last hydrotest chart, we build and look after the lines that carry the Delta's oil and gas.
- Service code
- PL
- Of line laid since 2009
- 412 km
- Weld repair rate, 2025
- 0.8%
- HDD crossings completed
- 31
Scope
We run conventional land spreads, swamp push-pull crews and tie-in teams. Integrity work runs alongside, so the people who build a line also know how it fails.
- Flowline and trunk line construction, 4 in to 36 in
- Swamp lay by push-pull and floatation methods
- Horizontal directional drilling crossings under creeks and roads
- Hot tapping, stoppling and live line tie-ins
- Integrity programmes: cathodic protection, clamp repair and sleeve installation
- Hydrotesting, dewatering, drying and nitrogen purging
A blue pipe section resting on excavated earth. Deltaline pipeline construction and integrity, illustrative photograph.
Capabilities
What we bring to site, in plain terms. Specifications and certificates for any item are shared with operators at tender stage.
Welding
Forty-two qualified welders across manual, semi-automatic and automatic processes, with procedures qualified per client specification.
Swamp spreads
Two complete swamp spreads with marsh excavators, pontoons and pull winches for mangrove and tidal routes.
Crossings
A 120-tonne HDD rig and a drilling fluid recycling plant for crossings up to 900 metres.
Integrity
Composite and steel sleeve repair, clamp installation and in-house cathodic protection survey teams.
Key equipment
Owned by Deltaline and maintained at Onne. The full register is on the fleet and equipment page.
Fleet and equipment| Item | Specification | Qty |
|---|---|---|
| Sideboom, 70 t | Pipe lifting and lowering-in | 8 |
| Marsh excavator, amphibious | Pontoon tracks, 21 t | 6 |
| HDD rig | 120 t pullback | 1 |
| Hot tap machine | Up to 24 in, 1,440 psi | 2 |
| Automatic welding system | Dual torch, internal clamp | 4 |
| Fill and test pump | 2,500 litres per minute | 3 |
How a typical project runs
Durations are typical for a mid-sized scope. Every programme is agreed with the operator before mobilisation.
Route survey
2 to 4 weeksRight-of-way walk with the operator and community liaison officers, ground survey and crossing studies.
Engineering
4 to 8 weeksWeld procedures, lay method, crossing design and a hydrotest plan, all submitted for operator approval.
Mobilisation and clearing
3 weeksSpread mobilised from Onne, right-of-way cleared, access matting placed in soft ground.
Lay, weld and coat
By kilometreString, weld, inspect, coat and lower in. Each joint is logged against its radiograph and coating test.
Test and hand over
3 to 5 weeksHydrotest, dewater and dry, then the as-built survey and turnover dossier.
Work in this discipline
| Ref | Year | Scope | Result |
|---|---|---|---|
| DL-PL-2269 | 2026 | Clamp and sleeve repairs on a 12 in crude line | 14 repairs, no shutdown |
| DL-PL-2229 | 2024 | 6 km swamp flowline by push-pull | Laid in 41 days |
| DL-PL-2152 | 2022 | HDD crossing of a 640 m estuary | Single pass pullback |