Replacing 18 km of 24 in gas line through Eleme and Okrika
- Reference
- DL-PL-2187
- Service line
- PL
- Duration
- 14 months
- Year
- 2024
A corroded 24 in gas line replaced alongside the live line, through farmland, creeks and three communities, with one planned shutdown.
Scope
- Route survey and right-of-way acquisition support
- 18 km of 24 in, API 5L X65 line pipe laid and coated
- Three HDD crossings under tidal creeks
- Hot tap tie-ins at both ends with a single planned shutdown
- Decommissioning and removal of the old line
The challenge
The existing line was losing wall thickness faster than the operator's integrity model predicted, and it fed a gas plant that could only accept a short outage.
The route crossed three communities with active farmland and two creeks used by fishermen every day.
Our approach
Lay beside the live line
The new line was built on a parallel right-of-way six metres from the old one, so gas kept flowing through construction.
Drill, do not dredge
Each creek was crossed by HDD instead of an open cut, which kept the water open to fishing boats and avoided disturbing the creek bed.
Communities in the plan
Each community nominated a liaison officer who sat in our weekly progress meeting. Seventy-one people from the three communities were hired and trained for the work.
-
Fig. 1. A metal pipeline running between trees in daylight. Select to enlarge.
-
Fig. 2. A blue and white coated pipe section. Select to enlarge.
Project figures
- Line length
- 18.2 km
- Diameter and grade
- 24 in, API 5L X65
- Welds completed
- 1,512
- Weld repair rate
- 0.7%
- Hydrotest pressure
- 2,160 psi, 24 hours
- Community hires
- 71
- Exposure hours
- 1,042,000
- Lost-time injuries
- 0
Timeline
- Mar 2023
Award and survey
Route walked with the operator and all three community liaison committees.
- Jun 2023
Engineering approved
Weld procedures, crossing designs and the hydrotest plan approved.
- Aug 2023 to Feb 2024
Construction
Lay, weld and coat, with the three HDD crossings completed in the dry season.
- Mar 2024
Tie-in
Hot tap tie-ins completed inside a 36 hour planned shutdown.
- May 2024
Handover
As-built survey, turnover dossier and removal of the old line.
The gas plant was down for a day and a half. We had planned for four.