← A Covorn template · Oil and gas services website Make it mine
DeltalineEnergy Services 24 h +234 84 460 1999
New pipe strings lined up along a cleared field

Replacing 18 km of 24 in gas line through Eleme and Okrika

Reference
DL-PL-2187
Service line
PL
Duration
14 months
Year
2024
18 kmof 24 in line laid
3HDD creek crossings
36 htotal shutdown for tie-in

A corroded 24 in gas line replaced alongside the live line, through farmland, creeks and three communities, with one planned shutdown.

Scope

  • Route survey and right-of-way acquisition support
  • 18 km of 24 in, API 5L X65 line pipe laid and coated
  • Three HDD crossings under tidal creeks
  • Hot tap tie-ins at both ends with a single planned shutdown
  • Decommissioning and removal of the old line

The challenge

The existing line was losing wall thickness faster than the operator's integrity model predicted, and it fed a gas plant that could only accept a short outage.

The route crossed three communities with active farmland and two creeks used by fishermen every day.

Our approach

Lay beside the live line

The new line was built on a parallel right-of-way six metres from the old one, so gas kept flowing through construction.

Drill, do not dredge

Each creek was crossed by HDD instead of an open cut, which kept the water open to fishing boats and avoided disturbing the creek bed.

Communities in the plan

Each community nominated a liaison officer who sat in our weekly progress meeting. Seventy-one people from the three communities were hired and trained for the work.

  • Fig. 1. A metal pipeline running between trees in daylight. Select to enlarge.

  • Fig. 2. A blue and white coated pipe section. Select to enlarge.

Project figures

Line length
18.2 km
Diameter and grade
24 in, API 5L X65
Welds completed
1,512
Weld repair rate
0.7%
Hydrotest pressure
2,160 psi, 24 hours
Community hires
71
Exposure hours
1,042,000
Lost-time injuries
0

Timeline

  1. Mar 2023

    Award and survey

    Route walked with the operator and all three community liaison committees.

  2. Jun 2023

    Engineering approved

    Weld procedures, crossing designs and the hydrotest plan approved.

  3. Aug 2023 to Feb 2024

    Construction

    Lay, weld and coat, with the three HDD crossings completed in the dry season.

  4. Mar 2024

    Tie-in

    Hot tap tie-ins completed inside a 36 hour planned shutdown.

  5. May 2024

    Handover

    As-built survey, turnover dossier and removal of the old line.

The gas plant was down for a day and a half. We had planned for four.

Project manager, operator's gas business
Next case study / DL-MR-2203 Three years of marine logistics for a Brass terminal expansion