← A Covorn template · Oil and gas services website Make it mine
DeltalineEnergy Services 24 h +234 84 460 1999
Grey industrial equipment inside a fabrication hall

Fabrication

Skids, spools, structures and process modules, built under cover at Onne and loaded straight onto a barge at our own quay.

Service code
FB
Yard at Onne
4.2 ha
Fabricated since 2014
18,600 t
Load-out quay rating
400 t

Scope

Our Onne yard runs two covered fabrication halls, a pipe shop, a blast and paint facility and a load-out quay. We fabricate to the operator's drawings or to our own detailed design.

  • Process and utility modules up to 650 tonnes
  • Piping spools in carbon steel, stainless and duplex
  • Platform structures, launchers, receivers and skids
  • Blast and paint to offshore coating systems
  • Load-out by self-propelled modular transporter to barge
Black and grey pipework close up

Black and grey pipework close up. Deltaline fabrication, illustrative photograph.

Capabilities

What we bring to site, in plain terms. Specifications and certificates for any item are shared with operators at tender stage.

Covered halls

Two halls totalling 5,600 square metres, with 40-tonne and 25-tonne overhead cranes.

Pipe shop

Bevelling, bending and automatic orbital welding for spools from 2 in to 36 in.

Coating

An enclosed blast room and a climate-controlled paint shop with humidity and dew point logging.

Load-out

A 180 metre quay with a 400-tonne rated load-out zone and SPMT hire arranged through our yard.

Key equipment

Owned by Deltaline and maintained at Onne. The full register is on the fleet and equipment page.

Fleet and equipment
ItemSpecificationQty
Overhead crane40 t, 32 m span2
Crawler crane250 t1
Orbital welding headTIG, 2 in to 12 in6
Plate rolling machine3 m width, 40 mm1
CNC plasma cutting table3 m by 12 m1
Blast room24 m by 8 m1

How a typical project runs

Durations are typical for a mid-sized scope. Every programme is agreed with the operator before mobilisation.

  1. Drawings and materials

    2 weeks

    Drawings checked, material take-off reconciled and mill certificates verified on receipt.

  2. Inspection and test plan

    1 week

    An ITP agreed with the operator, with hold and witness points marked before cutting starts.

  3. Fabrication

    By weight

    Cut, fit, weld and inspect. Daily progress against the weld log is shared with the client.

  4. Coating and testing

    2 to 4 weeks

    Blast, paint and hydrotest. Every coat is measured and recorded.

  5. Load-out

    1 to 3 days

    Weighing, sea-fastening design and load-out to barge at our quay, with the marine warranty surveyor present.

Work in this discipline

DL-FB-2265 / Case study A 540 tonne compression module, fabricated and loaded out at Onne 540 t module dry weight2,860 piping welds100% fabricated in Nigeria Read the case study
From the project register
RefYearScopeResult
DL-FB-22462025Pig launcher and receiver skids, 16 inDelivered 9 days early
DL-FB-21962024Platform boat landing and riser guardsInstalled in one weather window
Next service line / IN Inspection