Three years of marine logistics for a Brass terminal expansion
- Reference
- DL-MR-2203
- Service line
- MR
- Duration
- 36 months
- Year
- 2022 to 2025
Supply, crew transfer and heavy cargo moves for a terminal expansion, run from one marine operations room.
Scope
- Two platform supply vessels on time charter
- Three fast crew boats on a fixed daily schedule
- Tug and barge moves for 42 heavy cargo items
- Marine coordination and manifesting for all contractors on site
The challenge
Eleven contractors needed the same vessels, and each had been booking boats directly. Sailings were half empty one day and overbooked the next.
The approach to Brass is shallow and the bar is rough in the rainy season, which limits when heavy cargo can cross.
Our approach
One booking desk
We set up a single marine operations room at Onne and took over manifesting for all eleven contractors. Load factors rose from 54 to 81 per cent in the first quarter.
Tide windows planned weeks ahead
Heavy cargo was scheduled against tide and swell forecasts, with a fallback window always booked.
Crew boats on a timetable
Crew transfers ran to a published timetable, so the terminal could plan shift changes without calling us.
-
Fig. 1. A platform on the horizon over a flat sea. Select to enlarge.
Project figures
- Charter term
- 36 months
- Sailings
- 4,310
- Passengers moved
- 61,200
- Heavy cargo items
- 42
- On-time departures
- 98.6%
- Average load factor
- 81%
- Marine incidents
- 0
- Fuel saved against baseline
- 1.9 million litres
Timeline
- Apr 2022
Charter start
Vessels on hire, marine operations room opened at Onne.
- Jul 2022
Single booking desk
Manifesting for all contractors moved to Deltaline.
- 2023 to 2024
Peak construction
All 42 heavy cargo moves completed inside planned tide windows.
- Mar 2025
Charter close
Final performance review and off-hire surveys.
We stopped talking about boats in the morning meeting. That is how we knew it was working.