Dated reports from both estates, the same ones buyers receive each month. Filter by estate to follow the phase you care about.

Last update
3 Oct 2026
Gardens Phase 2
68%
Heights Phase 1
31%
Next report
1 Nov 2026
An aerial photograph of a settlement surrounded by green land

01Status board

Every phase at a glance

Percentages are weighted by cost across structure, roofing, services and finishes.

Gardens

Phase 2

Structure88%
Roofing22%
Finishes0%

Gardens

Phase 3

Survey100%
Groundworks6%
Structure0%

Heights

Phase 1

Structure31%
Roads40%
Gate55%

Example progress figures for this demo.

02Timeline

Reports, newest first

Planned work is shown with an open marker. Completed work is filled.

  1. Gardens Phase 2: roofing begins on block C

    Trusses lifted on 9 of 14 duplexes. Block D blockwork reached lintel level on all terraces. Drainage on Cedar Avenue extended to the Phase 3 boundary.

    Structural68%
    Roofing22%
    Services15%
    An aerial view of cleared grassland beside the estate
  2. Heights Phase 1: all slabs cast

    Twelve ground slabs cast and cube tested. Stepped raft foundations completed on the upper plots. Clubhouse design signed off.

    Structural31%
    Roads40%
    Services10%
    An aerial view of a field being worked by a tractor
  3. Gardens Phase 3: survey and pegging

    All 28 Phase 3 plots surveyed and pegged. Plot sizes confirmed against the approved layout. Off plan sales opened to existing owners first.

    Survey100%
    Groundworks0%
  4. Heights: main road and gate

    Main road base course laid and the gatehouse frame up. Transformer delivered and stored on site.

    Roads40%
    Gate55%
  5. Gardens Phase 2: plastering and first fix

    Planned: plastering across blocks C and D, first fix wiring and plumbing in the duplexes.

    Planned0%
  6. Heights Phase 2 release

    Planned: block K reservations open, clubhouse groundworks begin.

    Planned0%

Monthly report

On the first working day of each month: photos, percentages and next month's plan, by email and WhatsApp.

Quarterly site day

Owners walk the live build with our engineers on the last Saturday of each quarter.

Drone flyover

Every three months a short flyover video shows the whole estate from above.

03Get the reports

Receive the monthly report

Not an owner yet? You can still follow along. One email a month, nothing else.

Please fill this in.

Enter an email address like name@example.com.

Please fill this in.

The report lands the same morning every month. I forward it to my brother in Lagos and we both know exactly where our money is.
Ifeoma, example client, Gardens Phase 2

See the progress in person

Book an inspection and walk the live build with our site engineer.

Book inspectionCall sales