Line 2 back at full speed after upgrade

New roughing stands and a rebuilt cooling bed lift output on our second rolling line by eighteen percent.

An industrial complex lit up at night

What changed

During a planned twenty one day shutdown, the maintenance team replaced the first six roughing stands, rebuilt the cooling bed and installed new water boxes for quenching.

Why it matters

The upgrade lets Line 2 roll Y25 and Y32 at full speed, which used to be done only on Line 1. Lead times for heavy bar fall from five days to three.

Safety during the shutdown

Over 190 contractors worked through the shutdown without a lost time injury, under permit to work and daily toolbox talks.

What customers will notice

More heavy bar in stock, shorter waits for bridge and foundation orders, and the same certificates for every heat.

02Next

Read next

01

Better buy back rates for sorted heavy melting steel

Scrap sellers who sort heavy melting steel and remove non steel will see higher rates at the Idu weighbridge from October.

02

All news

Operations, prices, safety and community.

18%more output on Line 2
21days of planned work
0lost time injuries
420people at the mill