Case study
Auchi corridor
A 60 metre lattice tower and a fibre spur halfway to Auchi, built through the rainy season without losing a day to safety.
EDO-016, completed March 2026.
60 m
Metres of steel
18
Weeks, including the rains
2.4 km
Kilometres of fibre spur
0
Lost-time injuries
The brief
Coverage for a long, busy road
Travellers between Benin City and Auchi lost signal for long stretches. A rural connectivity fund and one operator asked for a tall tower that could also carry future tenants and a microwave relay.
The plot sat on soft ground beside a farm road. We laid the access road first, poured a raft foundation in two dry windows and kept a pump on site through August.
The tower carries a solar hybrid system sized for six tenants and a 2.4 kilometre fibre spur to the highway duct.
A tall tower on a farm road in the rains is not easy. They kept the farm family on side and the crew safe, and finished in March.
Timeline
How it went
June
Land agreed with the community and the farm family.
July to August
Access road and raft foundation between storms.
September to February
Steel, solar array and fibre spur.
March
Handover and the first operator live.
Good to know
About this project
Can more operators join?
Yes. EDO-016 has four free slots and fibre.
How is the site secured?
Fence, lighting, a resident guard and door alarms to our operations centre.