Building on lagoon sand
Seventy-two piles, a raft three metres thick and what the engineers found 40 metres down beneath Banana Island.
Long read, 9 minutes, by the engineering team (example)
Banana Island was made by people. In the 1970s and again in the 1990s, sand was pumped from the lagoon bed and built up into land, then left to settle. It makes a fine place to live and a difficult place to build tall. The top eight metres are that pumped sand, loose and wet; beneath it lie soft clays, then denser sands, and only at around 38 metres the firm layer engineers call the bearing stratum.
Seventy-two piles
A 48 level tower cannot rest on the top layers. Our structural engineers, Okonjo Structures (example), designed 72 bored piles, each 1.2 metres across, drilled to 40 metres and filled with reinforced concrete. Each pile was tested before the next stage began: a sound wave sent down the pile shows any flaw in the concrete, and three piles were loaded to twice their working load and watched for a week.
Most of the building's work is done before you can see any of it.
Drilling took fourteen weeks. The lagoon water table sits just a metre below the surface, so every bore was kept full of a bentonite slurry that holds the walls open until the concrete pushes it out from the bottom up. The slurry was cleaned and reused on site rather than tipped into the lagoon.
A raft three metres thick
The piles are tied together by a raft of reinforced concrete three metres thick, which spreads the weight of the tower across all of them. It took 4,800 cubic metres of concrete, poured in one continuous operation over 52 hours in July 2025, so that it would set as a single piece with no joints.
A pour that size generates its own heat. If the middle of the raft gets much hotter than its surface, it cracks as it cools. The mix used slag from steelworks in place of some of the cement, the pour started at night, and sensors cast into the concrete reported its temperature every ten minutes for three weeks while the surface was kept wet and covered.
What it means for owners
Settlement is the word engineers use for how much a building sinks as its weight comes on. The design allows for about 40 millimetres over the life of the tower, spread evenly; survey points on the raft are measured every month and have moved 11 millimetres so far, in line with the prediction. The figures are in the monthly report in the owner portal.
You will never see the piles or the raft. They are the reason the tower can be slender, why the lifts run true, and why your insurer asks fewer questions than you might expect for a building on reclaimed land.
In figures
- Piles
- 72, 1.2 m across
- Depth
- 40 m
- Raft
- 3 m thick
- Concrete in the raft
- 4,800 m³
- Pour
- 52 hours, continuous
- Settlement so far
- 11 mm of 40 mm allowed
About this long read
The figures in this piece come from the structural engineer's pile test reports and the monthly settlement survey, both of which owners can read in full in the owner portal. Depths are measured from the level of the arrival court. Ask the sales team if you would like to meet the engineer on a site visit.