Monthly site report
What changed on site this month
Photos and notes from our site engineers at Celestine Court and Ridge, updated every month. November 2026 report.
Progress
Where each block stands
Court, Block A
On time12 Iris homes. Roofs on, plastering inside, windows arriving next week.
74% complete
Court, Block B
On time12 Iris homes. First floor walls up, lintels cast.
48% complete
Court, Block C
One week behind8 Magnolia homes. Roofing 62% done, rains slowed us for a week.
62% complete
Court, Block D
On time16 homes. Foundations poured, blockwork starts in December.
18% complete
Ridge, roads
On timeAvenue kerbs laid, asphalt in January.
40% complete
Gardens, Phase 3 power
On timePanels delivered, battery house roofed.
55% complete
Example data for this demo.
Timeline
The last six months
- November 2026
Court Block C roofing
Roof trusses up on six of eight homes.
- October 2026
Ridge avenue kerbs
Two kilometres of kerbs laid.
- September 2026
Court Block A roofed
All 12 Iris roofs finished.
- August 2026
Phase 3 solar delivery
1,200 panels delivered and stored.
- July 2026
Court Block D foundations
Foundations poured and tested.
- June 2026
Ridge gatehouse finished
Gate, fence and guard house complete.
Photos
From the site this month
Questions
About building progress
Sign in to your account. Your home's stage photos and surveyor sign offs appear there.
Yes, with an escort, on weekdays between 10am and 3pm.
Our engineers, an independent surveyor and, if you like, your own.
Follow your own home
Owners see their stage photos, payments and documents in one place.