Projects / Case study 02 of 05 Completed 2023

The Alder

A 14-floor head office with a unitised curtain wall and two basement levels on a busy Victoria Island street.

A financial services group, owner-occupier / Victoria Island, Lagos / 28 months

The Alder, a brown and black commercial high rise
Client
A financial services group, owner-occupier
Location
Victoria Island, Lagos
Sector
Commercial
Delivery
Traditional, main contractor
Value band
₦12 billion to ₦18 billion
Duration
28 months
Floors
14 plus 2 basements
Size
21,400 sqm

The brief

A head office for 1,300 staff, with a banking hall at ground level, a trading floor at level 3 and two basement levels for 160 cars. The street outside carries traffic until late at night and the client wanted the building closed to weather before its second rainy season.

How we built it

We built the basement top-down, casting the ground floor slab early so the frame could rise while excavation continued below. That brought the frame programme forward by eleven weeks.

The unitised curtain wall arrived in numbered panels and was lifted in at night from a closed lane, two floors a week, with every bay water-tested before ceilings went in.

Mechanical and electrical works were coordinated in a single model with weekly clash reviews; the trading floor services were installed and tested as a separate early handover.

Outcome

The building was weathertight in month 19 and handed over in May 2023. The trading floor opened four weeks before the rest of the building, as the client had asked.

The project in figures

sqm of unitised curtain wall
6,800
basement car spaces
160
weeks saved by top-down basement
11
workplaces
1,300
standby generation
2.4 MW
lost-time injuries
0

Progress photographs

Select a photograph to enlarge it

  • Frame rising above the top-down basementSeptember 2021

  • Curtain wall installation on the north faceJune 2022

Key dates

From contract award to handover.

  1. 01Contract awardJanuary 2021
  2. 02Ground floor slab castJune 2021
  3. 03Frame completeApril 2022
  4. 04WeathertightAugust 2022
  5. 05HandoverMay 2023
Night lifts, a closed lane and not one complaint from the neighbours we heard about. The trading floor was live a month early.
Head of property, the client