Northern Link Road
A 7.4 km dual carriageway with 11 km of lined drains, three box culverts and two pedestrian bridges, built through two rainy seasons.
A public works agency / Kubwa, Abuja / 18 months
- Client
- A public works agency
- Location
- Kubwa, Abuja
- Sector
- Roads and drainage
- Delivery
- Employer's design, main contractor
- Value band
- ₦6 billion to ₦9 billion
- Duration
- 18 months
- Floors
- Not applicable
- Size
- 7.4 km dual carriageway
The brief
Upgrade a single-lane road into a dual carriageway serving fast-growing residential districts, keep the existing road open throughout, and stop the seasonal flooding that cut the route every August.
How we built it
We resurveyed the catchment before we touched the road. Three of the culverts in the original design were undersized for the storms recorded since 2018; we raised it with the engineer and the box culverts were enlarged before construction.
Drains and culverts went in first, section by section, so the new formation was never left exposed to standing water. Traffic ran on one half-width while the other was built.
Our Idu yard materials laboratory tested every layer of sub-base and base course before the next one was placed, and asphalt was laid in a single season to avoid cold joints.
Outcome
Opened to traffic in March 2025. Through the 2025 rainy season the route stayed open every day, the first year that has happened in local memory.
The project in figures
- km of dual carriageway
- 7.4
- km of lined drains
- 11.2
- box culverts, enlarged
- 3
- pedestrian bridges
- 2
- cubic metres of earthworks
- 46,000
- tonnes of asphalt
- 18,500
Progress photographs
Select a photograph to enlarge it
-
Culvert units lifted in at chainage 3+250October 2023
-
Morning briefing before the half-width switchMay 2024
Key dates
From contract award to handover.
- 01Contract awardSeptember 2023
- 02Drainage completeJune 2024
- 03Base course completeNovember 2024
- 04Surfacing completeFebruary 2025
- 05Open to trafficMarch 2025