Marina Point Residences
A 26-floor apartment tower on a narrow lagoon-edge plot, handed over three weeks ahead of programme.
A private residential developer / Ikoyi, Lagos / 34 months
- Client
- A private residential developer
- Location
- Ikoyi, Lagos
- Sector
- Residential
- Delivery
- Traditional, main contractor
- Value band
- ₦18 billion to ₦25 billion
- Duration
- 34 months
- Floors
- Ground plus 25
- Size
- 38,600 sqm
The brief
112 apartments and two penthouses on a 2,900 sqm plot at the lagoon edge in Ikoyi, with a two-level basement below the water table and one gate on a residential street. The developer had sold 60 per cent off-plan and needed a handover date buyers could rely on.
How we built it
We installed a secant pile wall around the whole basement and dewatered inside it, which let the excavation go down without disturbing the neighbouring houses. Settlement monitoring ran every day until the ground floor slab was cast.
Above ground we ran a jump-formed core one floor ahead of table-formed slabs, with concrete from our own batching plant timed to arrive in a single 06.00 window to avoid Ikoyi traffic. Once the cycle settled, a floor was completed every seven working days.
Façade and fit-out followed six floors behind the frame, with a sample apartment signed off by the developer at level 4 before any repetition started.
Outcome
Handed over in October 2024, three weeks ahead of the contract date, with 1.1 million hours worked and no lost-time injury. Defects at handover averaged 2.6 per apartment.
The project in figures
- bored piles to 32 m
- 186
- cubic metres of concrete
- 19,400
- tonnes of reinforcement
- 2,380
- working days per floor
- 7
- apartments plus 2 penthouses
- 112
- hours without a lost-time injury
- 1.1m
Progress photographs
Select a photograph to enlarge it
-
Frame at level 6 with the core two floors aheadMarch 2022
-
Table forms striking at level 14November 2022
-
Transfer level reinforcement drawing, revision DJune 2021
Key dates
From contract award to handover.
- 01Contract awardAugust 2021
- 02Basement completeJanuary 2022
- 03Frame topped outJuly 2023
- 04Façade closedFebruary 2024
- 05HandoverOctober 2024
They told us the floor cycle in the tender interview and then they held it for nineteen months. Our buyers moved in on the date we had promised them.