News / Engineering

How we hold a seven-day floor cycle on a Lagos tower

A floor a week sounds like a slogan. On Marina Point it was a schedule with 31 named tasks, and it held for nineteen months.

Published
Written by
Ifeoma Nwachukwu, Director of Engineering
Reading time
2 minutes
A grey and yellow tower crane above a site

When we tell a developer that a tower frame will rise one floor every seven working days, the first question is usually whether we mean it. We do, but only because the week is planned to the hour and the plan is the same on floor 4 as it is on floor 24.

The week, day by day

Monday the core form jumps and the table forms are flown up from the floor below. Tuesday and Wednesday are for slab reinforcement, sleeves and electrical conduits, with the services foremen walking the deck at 15.00 on Wednesday. Thursday is inspection: our engineer, the client's engineer and the services team sign one sheet. Friday morning the slab is poured from 06.00, before Ikoyi traffic builds.

That leaves the following Monday and Tuesday for curing and striking on the floor below, and the cycle starts again. If a pour slips, the slip is visible to everyone by Thursday afternoon, not three weeks later in a report.

What makes it possible

Three things matter more than anything else. The first is our own batching plant: concrete that arrives when we order it, at the slump we ordered. The second is a tower crane with nothing else to do on pour day; we move all other lifts to Thursday. The third is repetition. The design team agreed a standard floor early, so the formwork, the reinforcement schedules and the crew's habits are the same every week.

The cycle is not fast because people rush. It is fast because nobody waits.

Where it breaks

Transfer levels, plant floors and the roof break the rhythm, and we programme them as separate events with their own durations. Heavy rain stops pours, so the programme carries rain days between April and October. We would rather show a client those days on day one than explain them in month nine.