Drainage first: what the Northern Link Road taught us about Abuja rain
One year after opening, the road has stayed open through a full rainy season. The work that made the difference was underground.
Every August, before we arrived, the old Kubwa road flooded at the same three low points and traffic stopped for hours. The new dual carriageway opened in March 2025, and through the whole of the 2025 rains it did not close once.
Survey before you build
The original design used rainfall figures that were more than a decade old. Our survey team mapped the catchment again, including the new estates that now drain into it, and found that three culverts were too small for the storms recorded since 2018. We put the numbers to the engineer in writing in the first month; the culverts were enlarged before we ordered a single unit.
Build the drains before the road
We laid every drain and culvert in a section before we brought the formation up in that section. It costs a little more in sequencing and saves a great deal in rework: a formation left exposed to standing water for one storm can need to be dug out and replaced.
A road in this city fails at the drain long before it fails at the surface.
Keep the maintenance simple
Lined drains with access points every 40 metres, silt traps at every inlet and a maintenance manual written for the agency's own crews. The best drain is one that someone can clear with the tools they already own.